On the 8th of May the last deliveries of tunnel segments left the Shay Murtagh Precast factory for the CROSSRAIL C310 site in London.

This concluded just over 3,400 loads delivered to the site over a 2 year period.

C310 – is contracted to HOCHTIEF Murphy Joint Venture (HMJV), and in September 2012 HMJV awarded Shay Murtagh Precast the prestigious specialist manufacture of the precast concrete segmental tunnel linings.

 

Since then we have manufactured nearly thirty thousand individual precast concrete tunnel segments and transported same to the site.

In late May Shay Murtagh Precast Directors – Ciaran Murtagh and Liam McGovern along with Tunnel Manufacturing Manager Donal McGovern were on site at CROSSRAIL Thames Tunnel C310 for End of Tunnel.

Watch the “Fifteen Billion Pound Railway” on BBC2: http://www.bbc.co.uk/iplayer/episode/b04bwkj1/the-fifteen-billion-pound-railway-2-tunnels-under-the-thames

If you’re outside of the UK, you can watch the YouTube video here: The Fifteen Billion Pound Railway Episode 2

 

Shay Murtagh Precast Breakthrough at C310 Thames Tunnel

 

L to R: Donal McGovern (SMPL Tunnel Manager) Riku Tauriainen (HMJV Project Director )

Liam McGovern (SMPL Director) Stephan Assenmacher (HMJV Tunnel Construction Manager)

Ciaran Murtagh (SMPL Director)

For more about Shay Murtagh Precast Tunnel Segments contact the team at technical@shaymurtagh.co.uk

 

 

Gillian Murtagh

Gillian Murtagh

Gillian is the Marketing Director for Shay Murtagh Precast. The company's problem solving capacities allow us to give off site solutions to once insitu contracts which in turn speeds up project completion.

Working in conjunction with all divisions of the company she challenges industry norms in marketing.
Gillian Murtagh

    Share This

Post Comments 0