Irish Rail Project OB329, Charleville, Co. Cork

Shay Murtagh Precast Ltd. was selected by Irish Rail to design, supply and deliver Bedstones, Bridge Beams and Parapets on Bridge OB329 in Charleville, Co Cork over the busiest rail route in Ireland, the Dublin – Cork mainline. The original stone bridge was demolished in an 8-hour possession the previous night. The new structure was installed in a 9-hour possession.

Technical Information

Contractor: Irish Rail
Overall span: 10.5M and width 3.955M
Weights:
Bedstones, 13 Tons
2 No MY Beams, 24 Tons
MY Beam & Parapet, 30 Tons
Approach Wall, 15 Tons