Bridge Beams for Henrietta Street

As part of the work to electrify the rail line between Manchester and Stalybridge which is part of the £400m project to electrify key sections of the rail way across the North West, Henrietta Street over rail bridge, Ashton –under-Lyne was rebuilt to provide clearance for overhead lines.

Shay Murtagh Precast were contracted by Main Contractor J Murphy & Sons to manufacture and deliver precast elements.

The following precast elements were required

  • 11 number N2 approach parapet units varying in weight from 6.0t to 18.5t
  • 4 number cill beam units varying in weight from 14.8t to 21.0t
  • 2 number 21.550m long edge parapet beams with casting steel filler beams.

The East and West assemblies weighed 99.0t and 102.5t respectively. We worked closely with haulier JB Rawcliffe to deliver on schedule. J Murphy & Sons included the local school St Christopher's RC Primary School, who had been learning about the project during the year. The children designed safety posters to be used on the site, and as part of the opening in January 2014, a time capsule filled with items from the children's lives in 2014 was built into the bridge.

We thank Brendan, Martin, Paul and all the Murphy Team, and the JB Rawcliffe team for their professional, detailed and consistent involvement to project success.

Find out more about Shay Murtagh Precast Concrete Bridge Beams or contact the team at technical@shaymurtagh.co.uk for additional information.